Gantt chart for Projects Completed monthly

2 Posts
2 Users
0 Reactions
149 Views
(@qadeerhussain)
Posts: 1
New Member
Topic starter
 

Dear,

 

Our Projects are completed with month wise, How can i use Conditional formatting to show the start month and end month?

 

Awaiting your kind response.

 
Posted : 24/08/2020 10:13 am
(@mynda)
Posts: 4761
Member Admin
 

Hi Qadeer,

Welcome to our forum!

Your dashboard is structured a little different to mine in that you don't have the days completed. You can conditionally format the 'in progress' cells based on the start and end dates using this formula:

=AND($D7<=EOMONTH(J$6,-1)+1,$E7>=J$6)

 

Remember to select cell J7:AA35 then open the Conditional Formatting menu and insert the formula above.

Note: you need to start your dates at 31 Jul 2020 in cell J6.

Mynda

 
Posted : 24/08/2020 7:28 pm