Forum

Notifications
Clear all

Gannt chart

2 Posts
2 Users
0 Reactions
86 Views
(@ryan1990fisher)
Posts: 1
New Member
Topic starter
 

I followed one of Myndas tutorials which was excellent however I’m trying to use it for something it may not have been intended for and with a few tweaks it will be an excellent tool for my needs

 

i based it on the project management dashboard this one is actually built from the downloadable one 

 

what I am trying to do is make the Gannt chart show for labour allocation but it’s only filling the Gannt chart next to one of the allocation sites even though said person is allocated at 3 sites over different days also would be nice if I could colour code the Gannt chart per site 

 

can anybody help?

 
Posted : 22/02/2022 4:28 am
(@mynda)
Posts: 4761
Member Admin
 

Hi Ryan,

Welcome to our forum!

Your conditional formatting appears to be working correctly to me. Your dates span 2020 through to 2022, so you'll have to scroll a long way to the right to see the conditional formatting for 2022 dates because the first date in cell I5 is 17 Feb 2020.

Mynda

 
Posted : 22/02/2022 8:07 pm
Share: