RE: Using a Variable in Power Pivot

Hi Steve, 1. if you want all departments then don't include a parameter for department. Simply remove column H from the table in my example. 2. ...

9 years ago
Forum
Reply
RE: Add values from column C to the bottom of Column B

Hi Bill, Thanks for sharing your data. You will have to clean one class at a time because the original data layout is not consistent i.e. the numbe...

9 years ago
Forum
Reply
RE: Using a Variable in Power Pivot

Hi Steve, If you're using Power Query to get your data from your SQL DB and load it into Power Pivot, which you should be, then you can use a param...

9 years ago
Forum
Reply
RE: Printing Slicers in a more readable format

Hi Pamela, I'm not familiar with printing problems with Slicers. I did some Google searches and couldn't find any mention of this either. Instea...

9 years ago
Reply
RE: How to add a column (List of Date) using excel named ranges e.g. Project_Start_ Date and Project_End_ Date

Hi Hasnat, You can also use the list generator shortcut of two dots .. with Number.From to generate the list of dates using this M code: let ...

9 years ago
Forum
Reply
RE: Add values from column C to the bottom of Column B

Hi William, Firstly, I've moved your question to our Power Query Members forum. The forums at the top are for non-members. Session 3.04 of the P...

9 years ago
Forum
Reply
RE: Slicer

Hi Mey, Unfortunately the 'All Data' worksheet is not in the ideal layout for working with the built in tools that make this task easy e.g. Slicers...

9 years ago
Reply
RE: How to add a column (List of Date) using excel named ranges e.g. Project_Start_ Date and Project_End_ Date

Hi Hasnat, The StackOverflow solution is for getting a file path. It does not work with dates. Your solution, or mine is fine. Many steps doesn'...

9 years ago
Forum
Reply
RE: How to add a column (List of Date) using excel named ranges e.g. Project_Start_ Date and Project_End_ Date

Hi Hasnat, In the attached file I've given the dates the following named ranges: StartDate EndDate 1. Create a blank query and used the =E...

9 years ago
Forum
Reply
RE: Windows 10 and PQ Support

I'd say it's just out of date documentation on that page. I'm not aware of any official mention that Windows 10 doesn't support Power Query. Anyhow...

9 years ago
Forum
Reply
RE: Windows 10 and PQ Support

Hi Chad, What makes you think you don't have Power Query in Excel 2016 on Windows 10? I have that setup and I have Power Query. Could it be that...

9 years ago
Forum
Reply
RE: Chart format plot area doesn't save changes when changing slicer

Hi Theresa, If they're PivotCharts then this is a known bug i.e. PivotCharts lose formatting upon refresh (sometimes!). That said, I don't recom...

9 years ago
Reply
RE: Download of forecast data

I suspect so, but wanted to check if that could be the cause before I go back to Microsoft and ask. I'll see what I can find out.

9 years ago
Forum
Reply
RE: Compare a transaction date (value) against a point in time (measure) with a True and false outcome

Hi Amber, Add your calculated column to Table two. This is your fact table with the transactions. You need to classify each transaction into when i...

9 years ago
Forum
Reply
RE: No accees to data model through menu to Manage Data Model

Hi Tony, What version of Excel are you using? Mynda